Xinyu Feihu: D159 chilled water pipeline with non-stop transmission was performed two cylinder type single plugging operation

Xinyu Feihu: D159 chilled water pipeline with non-stop transmission was performed two cylinder type single plugging operation

In the science and Technology Research and development center of the head office of the Bank of Beijing, Mapo Town, Shunyi District, Beijing, China Construction Technology Group Co., Ltd. needs to seal the valve of the chilled water supply pipeline with continuous transmission and pressure cylinder in the two water pipe Wells on the east and west sides of the third floor of the A1 building of the research and development center. The company decided to invite a professional construction team for hot tapping and plugging to be responsible for the implementation.

On June 14, 2023, the professional construction team of Xinyu Feihu Pipeline Technology Equipment Co., Ltd. arrived at the site. After full preparation in the early stage, the 5 operators cooperated in strict accordance with the construction plan, and carried out a series of operating procedures such as pressure welding, opening, blocking, plugging and installing blind plates in an orderly manner. Lasted for 2 days, on the D159 chilled water pipe, two cylinder type single plugging operation was done, successfully completing the task, and Xinyu Feihu was highly appreciated by the owner.