On March 29, 2024, Xinyu Feihu carried out the dn250-SDR11 ultra high flow rate (25 meters/second) PE natural gas pipeline double plugging project in Suichuan, Jiangxi, replacing about 300 meters of pipeline section.During construction, it’s without shutdown. The pipeline design pressure was 0.4MPa, and the pipeline operating pressure during construction was 0.3MPa.